Harness Development Stages: From Drawing and Prototype to Series Production

What is delivered at each stage from drawing review to series production.

Share

A harness does not go from drawing to production in one step. Each stage exists to find a different type of fault, and skipping one moves the cost of that fault to a later and more expensive stage. This guide describes the usual stages so that the buyer and the manufacturer agree up front on what is delivered at each one. APAR builds harnesses to customer drawings, as described on its automotive and EV harness and railway coach harness pages.

StageWhat is deliveredWhat it finds
1. Drawing and bill of materials reviewReleased drawing, bill of materials and the list of open queriesMissing dimensions, unclear part numbers, parts on long lead time
2. PrototypeA small number of harnesses, often hand-built on a formboardFit problems on the vehicle or coach, wrong lengths, wrong breakout positions
3. First article inspectionOne harness checked fully against the drawing, with a record of every dimension and testDifferences between the drawing and the real part
4. ValidationSamples tested for the stated environment, such as temperature, vibration, sealing or fire performanceFailures that only appear under stress
5. ApprovalWritten sign-off by the buyer of the drawing revision, parts and processDisagreement on what was approved
6. Series productionProduction harnesses, each tested before dispatchProcess variation, damaged or wrong parts
7. Change controlA revision issued and approved before any part, wire or process changesUnapproved substitutions

Points to settle early

State at enquiry how many prototype pieces are needed and who pays for tooling. Agree which tests the first article must pass and whether the buyer will witness them. In automotive work the buyer may also require a formal production part approval process, and the manufacturer needs to know that before it quotes. APAR’s automotive harness page lists IATF 16949 and ISO 9001:2015 among its quality approvals, and states that harnesses are cut, crimped, routed and tested before delivery.

The first article should be kept as a reference. Later production lots can then be compared against a known approved part when a question arises. The harness testing guide lists the checks usually run at stage 3 and stage 6, and the RFQ checklist covers what the buyer should supply to start stage 1.