A correctly sized pump cable can still fail early if it is damaged on the way down the borewell. Cuts at the well head, clamps that bite into the sheath and a hurried joint above the motor account for many cable faults on submersible sets. This checklist follows the job in order, from the checks before lowering to the readings to record afterwards. It assumes the cable has already been sized. The pump maker’s installation manual governs where it differs.
1. Before the pump goes down
- Confirm that the cable is a flat 3-core submersible type and that its size suits the motor current and the full cable length, meaning the surface run plus the drop. The submersible pump cable selection guide covers sizing.
- Run the whole length through the hands and look for cuts, flattened sections and kinks. A damaged length should be cut out before lowering, not after.
- Measure the insulation resistance of the cable and of the motor before they are joined, and write the readings down.
- Check that the cable is long enough to reach the starter without a second joint at the surface.
2. The joint between motor lead and drop cable
- Use a jointing kit made for continuous immersion and matched to the cable size.
- Stagger the three conductor joints so that they do not sit side by side.
- Crimp the connectors with the correct tool. Twisted and taped conductors are not a submersible joint.
- Follow the kit instructions in full and keep the work clean and dry.
- Measure insulation resistance again once the joint is complete, with the joint immersed in a bucket of water where the kit instructions allow it.
3. Lowering
- Never lower, hang or lift the pump by its cable. The riser pipe, or the rope or wire provided for the purpose, carries the weight.
- Fix the cable to the riser pipe as the pipe goes down, at the spacing the pump maker specifies. Use clamps or ties that hold the cable without cutting into the sheath.
- Lay the flat cable flat against the pipe, without twists.
- Leave a little slack between fixings so that the cable is not stretched when the pipe takes the load.
- Protect the cable where it passes over the edge of the casing and through the well cap. This is the most common place for sheath damage.
4. From well head to starter
- Protect the surface run in conduit or by burial, and bring it into the starter through a proper gland.
- Connect the earth and confirm earth continuity to the pump set.
- Set the starter overload to the motor nameplate current.
5. Readings to record on the day
| Reading | When | Why it is kept |
|---|---|---|
| Insulation resistance, cable and motor | Before lowering, after the joint and after installation | A fall between readings points to damage during lowering |
| Running current on each phase | With the pump delivering water | Compared with the nameplate, and with later readings |
| Voltage at the starter while running | With the pump delivering water | Shows whether the supply and the cable are giving the motor enough voltage |
| Cable size, length and joint position | At installation | Needed when the pump is next pulled |
6. Each time the pump is pulled
- Inspect the sheath at every fixing point and at the well head.
- Repeat the insulation resistance test and compare it with the installation record.
- Replace a cable that shows cuts through the sheath. Tape is not a repair for a cable that works under water.
Choosing the cable
APAR makes three flat 3-core cables for submersible pump sets. Shakti Flat Multicore is the PVC copper cable, published from 1.5 to 50 sq mm. Mahashakti Flat Multicore has XLPO insulation and an elastomer sheath, also from 1.5 to 50 sq mm, and is the grade to consider where the pump runs long hours or is pulled often. Alumshakti Flat Multicore is the aluminium version, from 2.5 to 16 sq mm.
This checklist describes general good practice. Installation should be carried out by a trained pump installer or a licensed electrician.