Wiring Harness RFQ Checklist: Drawings, BOM and What Sets Lead Time

What to send with a harness enquiry so the quote is accurate and the first article is right.

Share

A harness enquiry that arrives as a photo of a sample and a quantity can be quoted, but the quote will carry assumptions, and every assumption is a risk to price, lead time and fit. An enquiry with a complete data pack is quoted faster and more tightly, and the first article is far more likely to be right. This checklist covers what to send.

Drawings

Send the harness drawing at its current revision, showing the layout, branch lengths and take-out positions with tolerances, and the connector views. If the harness is built on a formboard at full scale, say so. For rolling stock and locomotives, include the relevant schematic or wiring diagram reference.

Wire list

A from-to list gives every circuit: its number, wire type, size and colour, and the connector and cavity at each end. The wire list is what the continuity tester is programmed from, so errors in it pass straight into the product.

Bill of materials

ItemWhat to specify
WireStandard and type (for example ISO 6722 class, FLRY-B, AVSS, GXL, or rail cable to ELRS or EN specification), size and colour
Terminals and connectorsManufacturer and part number, plating, and whether an equivalent is acceptable
Seals and cavity plugsPart numbers matched to wire insulation diameter
ProtectionConduit, sleeving, tape or overmould, with material and fire rating where required
IdentificationLabels, ferrule markers, sleeves and their text

Requirements

State the tests to be performed and recorded, the workmanship standard, and the applicable specifications. For railway coach and locomotive harnesses these are usually the EDTS and RDSO specifications named on the drawing; for rolling stock built to European practice, the EN 45545-2 hazard level. For vehicles, state any customer approvals required. Give annual volume, batch sizes and the call-off pattern, and the packaging and labelling needed at the receiving line.

What sets lead time

The longest item usually decides the date. For many harnesses that is a connector or terminal with a long factory lead time, particularly where the drawing names one manufacturer’s part with no approved equivalent. Crimp applicators for a new terminal family, a formboard for a new layout, and special wire that has to be produced to order also add time. First-article approval sits on the critical path for any new part number, so a prompt review by the customer shortens the overall programme. Flagging which components the customer will free-issue, and which the supplier should buy, removes a common source of delay.