Cable Schedule Guide: Columns to Include and a Layout That Orders Correctly

One schedule that ties every cable to its source, destination, size and route.

Share

A cable schedule is the document that ties every cable in a project to its source, destination, size and route. A complete schedule lets the purchasing team order the right lengths, lets the installer pull the right cable, and lets the maintenance team find the cable years later. Gaps in the schedule show up on site as wrong lengths, wrong sizes or cables with no clear owner.

Columns to include

ColumnWhat to recordWhy it matters
Cable numberA unique tag, repeated on the cable at both endsThe link between drawing, cable and test record
From and toSource and destination equipment tags, with panel and terminalDefines the run and the routing
ServicePower, control, instrumentation, data, earthingDrives segregation in trays
Voltage gradeFor example 600/1000 VSets insulation level
Cores and sizeNumber of cores and conductor area, with conductor materialThe core of the order
ConstructionInsulation, armour or screen, sheath gradeFire, mechanical and interference performance
StandardApplicable standard, for example IS 7098 Part 1Basis for testing and acceptance
Design currentFull-load current and, where relevant, starting currentInput to the size check
Route lengthMeasured route length, plus the allowance for terminationsBasis for drum planning and for the voltage-drop check
Voltage dropCalculated percentage at full load and, for motors, at startingConfirms the size chosen
Tray or routeTray, conduit, trench or duct referenceCoordinates cables with containment
TerminationGland type and lug type at each endPrevents ordering errors for accessories
RemarksSpecial conditions, such as hazardous area or fire survivalCatches exceptions

Example row

FieldEntry
Cable numberP-101
FromMCC-1, feeder 4
ToPump 1 motor terminal box
ServicePower
Voltage grade600/1000 V
Cores and size3.5 core, 70 mm², aluminium
ConstructionXLPE, steel wire armoured, PVC sheath
Route length85 m

The example values are placeholders to show the layout and are not a recommendation for any load.

Good practice

  • Build the schedule in a spreadsheet, so lengths and voltage drops are calculated from the same data that goes into the order.
  • Add the spare core count for control cables at the planning stage. The control cable core-count and spare-core planning guide covers this in detail.
  • Issue the schedule with a revision number, and update it when the routes change.
  • Send the final schedule, or the extract for the order, with the enquiry. The cable enquiry specification sheet lists what a manufacturer needs to quote.

For the cable constructions APAR makes in low-voltage power sizes, see LV XLPE insulated power cables, and for the cores and conductor sizes in control cables see LV XLPE/PVC control cables.