Covered Conductor Site Survey Checklist: What to Record Before Specifying

The line, route, climate and fault data to gather before a covered conductor enquiry or tender.

Share

Most revisions to a covered conductor order trace back to data that was missing at enquiry stage: a span that turned out longer than assumed, a crossing nobody listed, a pole type that was never checked. A short survey avoids them. Use the checklist below on each feeder section, then carry the answers into the tender specification checklist or an enquiry to APAR.

Line data

RecordWhy it matters
Nominal voltage and system earthingDecides the voltage class. APAR covered conductor is offered at 11, 22, 33, 66, 110 and 132 kV.
Existing conductor type and sizeSets the starting point for the replacement size, within the 100 to 400 mm² range offered.
Span lengths, longest and typicalDrives the choice of conductor core and the sag check.
Pole type, strength rating and conditionThe covering adds weight compared with a bare conductor of the same size.
Cross-arm and insulator typeCovered conductor is designed to be installed without changing poles, cross-arms or insulators in the same span, which holds only if these are sound.
Number of circuits and phase arrangementAffects accessories and clearance checks.

Route and crossings

RecordWhy it matters
Vegetation type and height beside the lineTree and creeper contact is the usual reason to move to covered conductor. See tree contact on 11 kV and 33 kV feeders.
Forest, wildlife or plantation sectionsMarks where animal and bird contact is likely.
Road, rail, river and canal crossingsEach crossing has its own clearance and approval requirements from the owner of the asset.
Dense housing or built-up sectionsMarks where narrow corridors and public safety weigh most.

Environment

RecordWhy it matters
Distance from the coast, industrial emissions, dustSalt and pollution affect the covering surface and the choice of core.
Wind exposure and storm historyConductor clashing is a wind-driven fault.
Flood or waterlogging riskAffects drum storage and pole base checks.

Fault and load history

RecordWhy it matters
Trip log for the last two years, split into transient and permanentShows which spans cause the outages. Transient trips that clear on reclosure often point to contact faults.
Weather on the day of each tripSeparates wind-driven and storm faults from the rest.
Peak load current and ambient temperatureChecked against the covered conductor operating temperature of up to 95°C, or 105°C for AL59 ACS.
Fault level at the source endNeeded for the protection and arc protection design.

Constraints on the work

Note the permitted outage windows, access for drum delivery and stringing equipment, and any section that cannot be shut down. Delivery planning is covered in the drum handling and site receipt checklist.

Sending the survey to APAR

Share the completed checklist with the enquiry on the covered conductor page. Technical particulars, test certificates and samples are available on request.